Installing a meter

A meter has to be installed if you want:

  • a meter at a new place of consumption;
  • to replace a single-phase meter with a three-phase meter; or
  • to change the location of your meter.
  • The order of work is different and depends on whether it is done in an apartment building or a private house, and which meter-related work is performed.

    Apartment building

    Installing a meter may be required if a new place of consumption is built in the apartment building, such as a new apartment.

    Replacing the meter may be required if you want to replace a single-phase meter with a three-phase meter.

  • Installing a three-phase meter requires the connection point of your apartment building to have a three-phase network connection.
  • Order installation of a meter

    Private house

    If you want to replace a single-phase meter in a private house with a three-phase meter, submit an application to transfer the connection point to a three-phase network connection.

    Submit an application

    Works in an apartment building

    Get consent

    Get written consent from the apartment association or residents of the building to install or replace the meter.

    Organise the required work

    Arrange the work outlined in the technical inspection document to be done by a licensed electrician:

    Transfer of the place of consumption in an apartment building from single-phase to three-phase (pdf) »
    Installation of a meter in an apartment building (pdf) »

    Place an order

    When the works outlined in the technical inspection document are completed, place an order.

    Order installation of a meter »
    When placing an order, attach the consent document.

    We install or replace the meter

    How much does it cost to install or replace a meter?

    Installing or replacing a meter

    61.20 € *


    *A sealing fee will be added to the meter installation fee if the meter is sealed at a different time from when the meter is installed.

    If it turns out that at the place of consumption the customer has not done the necessary work, a call-out fee of €30.00 will be added.

    Apartment building

    If you want to move the meter from one wall to another or from your apartment to the corridor:

  • Carry out preparatory works in accordance with the technical inspection document.
  • Order seal removal
  • Move the meter to a suitable location.
  • Sealing the meter.
  • Private house

    If you want to move the meter out of the house:

  • If moving the meter changes the location of the connection point (eg you want to move the meter onto a pole), order changing the location of the connection point.
  • See the location of your connection point in the self-service of the network contract page.
  • If moving the meter does not change the location of the connection point (eg you want to move the meter to an outer wall of the house or from one wall to another in the house):

  • Carry out preparatory works in accordance with the technical inspection document.
  • Order seal removal.
  • Move the meter to a suitable location.
  • Sealing the meter.
  • How much does it cost to change the location of the meter?

    Changing the location

    The fee depends on the price offer of the selected electrical company.

    A sealing fee will be added

    36.00 – 37.20 €


    If it turns out that at the place of consumption the customer has not done the necessary work, a call-out fee of €30.00 will be added.

    What should I do before a meter can be replaced?

    Submit a written consent of the owner or manager of the building to replace the meter with a three-phase meter.

    The work must be arranged as outlined in the standard technical inspection document and in the design, where a design is necessary. The qualified company you have chosen to do the electrical work will decide if a design is needed. You need not submit the design to us.

    Some work has to be done in your meter before a three-phase meter can be installed, including:

  • Installation of a three-phase mains cord from the switchboard or connection point to the main fuse of the apartment
  • Replacement of the apartment's single-phase main fuse or circuit breaker with a three-phase one
  • Preparation of wires for connection to a three-phase meter.
  • The connecting party must prove the suitability of the electrical installation with an audit or letter of confirmation by the builder, according to the Device Safety Act.

    After you have finished the preparation work we will install a new remotely read three-phase meter.

    Work required if you want to change the location of your meter

    Request a technical inspection document from us to change the location of a meter or build a new metering point. This will tell you if you have to get a reconstruction project for the internal electrical system.

    The work must be arranged as outlined in the standard technical inspection documentand in the design, where a design is necessary.

    Where the main fuse is over 80 A, you should order and submit to us notification that the electrical installation has been accepted into service along with a copy of the audit.

    After you have finished the preparation work we will install a new remotely read meter.