Available capacities
The available capacities map provides an overview of the unused resource of medium voltage power lines. The map is based on calculations of medium voltage lines and shows which lines do not need costly distribution network construction works in order to create a new network connection with the displayed capacity, thus helping to plan connections to more efficient locations in terms of both production and consumption.
The capacities shown on the map are for information only. The display of available capacities takes into account existing electricity producers, pending and undeveloped connections, but does not take into account available capacities between the distribution and the transmission network.
The interactive medium voltage line map shows the available production-oriented power lines capacity in different colors. An explanatory legend opens on the top right corner of the map. Zoom in close enough to see available capacities of the power lines on the screen.
NB! The map of available capacities shows indicative information, and the final answer regarding the connection costs can be obtained by submitting a connection application.
Subscription and subscription fee
In the case of an energy-intensive electricity producer and a medium-voltage consumer willing to connect, the connection fee is formed according to the actual costs necessary to build a connection with the desired capacity. In the absence of sufficient capacity, the need to carry out the reconstruction of the distribution network must be taken into account.
The connection of the applicant to the distribution network may reveal that the distribution network operator and the transmission grid operator have to agree on new conditions of consumption and/or production, which may lead to the reconstruction of the transmission grid.
To find the available capacities in the distribution network, see the map application below. To find out the exact connection fee and connection deadline an application must be submitted.
You can submit a connection application via our e-service.
Elering map application e-Gridmap
The transmission grid operator Elering also has an interactive map application for displaying available connection capacities and approximate connection costs in regional substations.
Frequently Asked Questions
The calculation of free capacity is based on medium voltage lines and takes into account the constraints arising from the lines. Free capacity depends mainly on the change in voltage on the line, and after a producer connecting to the network, the voltages in the grid must remain within the permitted limits. As the voltage change along the line increases, it is possible to connect higher capacities to the beginning of the line from the supply substation and increasingly smaller ones further down the line.
The calculations take into account the current configuration of the medium voltage lines and producers that have joined so far, as well as the throughput limits of the grid with the added production. The calculations do not take into account the throughput of the transmission network or activities related to the construction of the connection point, such as the need to build a new substation to the line at the connection point.
The map of free capacities shows indicative information, and the final answer regarding the connection costs can be obtained by submitting a connection application. We process connection applications in the order in which they are received, and the information on the map does not change the order of processing.
It is also important to take into account that the information on the map is based on the current grid configuration and does take into account pending requests or pending connections, but does not take into account the throughput of the transmission network or a possible need to build a substation on the line. Therefore, in the case of an application within the available capacity on the map, it may still be necessary to contact the transmission network operator during the procedure or to rebuild the elements of the power network to allow connection.
Elering's interactive map application
Any differences between the resources shown on the Elering and Elektrilevi maps are due to the fact that Elering's map shows available capacities at 110 kV that apply to customers who are joining the transmission system and need a new network connection.
Eleketrilevi's map shows the available capacity on the low voltage side of the substation (at 6, 10, 15 or 20 kV depending on the substation) and takes into account the network contract with the transmission network, the capacity of the substation's equipment, and the network and connection contracts signed with existing customers.
If the customer connecting to the transmission network wants access to higher capacity than that displayed on the map, then the actual work volume and time cost required for connection will be determined in the process of preparing a connection offer.