Connection for small producers (under 500 kW)

Small producers with electricity production capacity below 500 kW are welcome to join our electricity network. In addition to consuming high-quality electricity the excess electricity can be sold to a suitable electricity seller.

Connection application with documentation

To receive a connection quotation, you have to submit a connection application and other relevant documentation. This can be done by e-mail or regular mail.

Submit an application
elektritootjad@elektrilevi.ee
Download an application form

Connection process

Submit a connection application

We can use the connection application to prepare a quote.

Signing a connection contract

We will sign a connection contract and begin the construction work required for the connection once the first instalment has been paid.

Commissioning small production equipment

To be able to start using your production equipment, send us a report on how the safety settings of the production equipment are set and a copy of the conformity audit report.

Signing a network contract

You need a network contract to be able to use the network connection.

Buying and selling electricity

To buy and sell electricity, you will have to sign an electricity contract with an electricity seller

Read more about the steps

How much does connection cost for a small producer?

If the transmission capacity of the electricity network is sufficient, the following investments will be required:

  • a meter suitable for production purposes
  • an isolating switch to assure safety
  • If the transmission capacity of the electricity network is not sufficient and needs to be increased, you will also have to pay for the necessary work and equipment and materials.


    The connection fee is always based on actual costs, the exact amount of which and the connection time will be clarified in a connection quotation.

    How long does connection take?

    If no additional work needs to be done in the electricity network, then connection can take

    up to 2 months


    If additional work needs to be done in the electricity network, then connection can take

    up to a year

    What equipment is suitable?

    See what equipment is compatible with our network.

    Equipment list

    If your selected equipment is not on our list, you should submit the appropriate documents concerning the model.
    Read more »

    Steps to connection

    We can use the connection application to prepare a quote.

    To receive a connection quotation, submit a connection application (doc). After receiving your connection application, we will send you a cost-based contract offer. The connection fee is indicative.

    When preparing a contract offer for an electric power station over 200 kW, Elektrilevi might discover that the throughput into Elering's network has to be increased. In such case, you have to pay Elering's processing fee (1600 euros + VAT) according to the transmission network price list to receive a contract offer. The costs specified in Elering's contract offer will be added to your contract offer.

    The connection costs might increase or decrease in comparison to the original offer during the connection work. The connection fee will be offset with the last instalment after the construction has been completed.

  • If you are not the owner of the property you are using, you also must include the owner's letter of authorisation with your application.
  • In case of a common ownership, the written approval of the co-owner must be included.
  • If you want to join as a producer in an apartment complex or a row house, you must also include the written approval of the apartment association or all co-owners with you application.
  • The forms for letters of authorisation and approvals are available under Conditions and forms »

    We will sign a connection contract and begin the construction work required for the connection once the first instalment has been paid.

    You have 60 days to review the connection offer. If you accept the terms we will start the construction work after the first instalment of the connection fee has been paid. The size of the first instalment is:

  • 50% of the connection fee, if the total connection fee is up to 6,000 euros.
  • 10% of the connection fee, if the total connection fee is over 6,000 euros.
  • To be able to start using your production equipment, send us a report on how the safety settings of the production equipment are set and a copy of the conformity audit report.

    To be able to start using your production equipment, send us the following documents:

  • a report on how the safety settings of the production equipment are set »
  • A valid notice of conformity with all requirements for the electrical system issued by the installer of the equipment, and a copy of the conformity audit report. Details of when an audit is required »
  • You need a network contract to be able to use the network connection.

    We will sign the network contract after you have submitted all the necessary documents and paid the bills. You need a network contract to be able to use the network connection, including to transmit electricity and measure its consumption.

    To buy and sell electricity, you will have to sign an electricity contract with an electricity seller. You will find information on electricity sellers on our website.